Legislation Validation Ordinance

TURKS AND CAICOS ISLANDS ELECTRICITY (VALIDATION) ORDINANCE 2018

Published
August 3, 2018
Notice Date
July 26, 2018
ID
TCI-169-33-046
Authority
Legislature of the Turks and Caicos Islands
PDF Pages
62, 63, 64

Summary

The Ordinance validates the deemed commencement of the Electricity Ordinance in North Caicos, Middle Caicos and the rest of the Turks and Caicos Islands, and validates specified regulations, rates, charges, collections, penalties, and acts or omissions.

Entities (5)

NameTypeRolesRegistration IDs
Electricity (Validation) Ordinance 2018 other validating ordinance, enacted legislation Ordinance 18 of 2018
Legislature of the Turks and Caicos Islands government_agency enacting legislature —
Governor of the Turks and Caicos Islands person may appoint the commencement day by Gazette Notice —
Electricity Ordinance
aka: principal Ordinance
other principal Ordinance whose commencement is validated —
Electricity Rates and Charges Regulations (Providenciales, North Caicos and Middle Caicos) other regulations validated by the Ordinance —

Events (12)

  • July 26, 2018
    assent
    Status: assented
  • August 3, 2018
    publication
    Status: published in Gazette
  • Date unknown
    commencement_provision
    Status: to come into force on a day appointed by the Governor by Notice published in the Gazette
    Authority: Section 1 of the Electricity (Validation) Ordinance 2018
  • April 1, 1986
    commencement_of_principal_ordinance
    Status: deemed to have come into force
    Authority: Section 3(1) of the Electricity (Validation) Ordinance 2018
  • April 1, 1986
    commencement_of_principal_ordinance
    Status: stated to have been brought into force
    Authority: Section 2(2)(a) of the Electricity (Validation) Ordinance 2018
  • December 12, 1986
    commencement_of_principal_ordinance
    Status: stated to have been brought into force
    Authority: Section 2(2)(b) of the Electricity (Validation) Ordinance 2018
  • February 1, 1987
    commencement_of_principal_ordinance
    Status: stated to have been brought into force
    Authority: Section 2(2)(c) of the Electricity (Validation) Ordinance 2018
  • Date unknown
    validation_of_regulations
    Status: validated
    Authority: Section 4(1) of the Electricity (Validation) Ordinance 2018
  • April 1, 2012
    validation_of_rates_and_charges
    Status: declared lawfully made from this date
    Authority: Section 4(2) of the Electricity (Validation) Ordinance 2018
  • April 1, 2012
    validation_of_collections
    Status: declared lawfully collected from this date
    Authority: Section 4(2) of the Electricity (Validation) Ordinance 2018
  • April 1, 2012
    validation_of_penalties
    Status: declared lawfully imposed from this date
    Authority: Section 4(2) of the Electricity (Validation) Ordinance 2018
  • Date unknown
    validation_of_acts_and_omissions
    Status: deemed validly and properly done or omitted
    Authority: Section 5 of the Electricity (Validation) Ordinance 2018

Legal Authorities

Electricity (Validation) Ordinance 2018 ordinance No. 18 (2018)
Relationship: cited
Electricity Ordinance ordinance
Section sections 2(1), 2(2), 3(1), 3(2), and 5
Relationship: cited; commencement and acts or omissions relating to it are validated
Electricity Rates and Charges Regulations (Providenciales, North Caicos and Middle Caicos) regulation
Section section 4(1) and (2)
Relationship: cited; regulations, rates, charges, collections, and penalties are validated

Relationships

SubjectRelationshipObjectType
entity-1 enacted_by entity-2 explicit
entity-1 provides_for_commencement_by_notice_appointed_by entity-3 explicit
entity-1 validates_commencement_of entity-4 explicit
entity-1 validates entity-5 explicit

Full Text

1 TURKS AND CAICOS ISLANDS ELECTRICITY (VALIDATION) ORDINANCE 2018 (Ordinance 18 of 2018) ARRANGEMENT OF SECTIONS SECTION 1. Short title and commencement 2. Purpose 3. Validation of commencement of principal Ordinance 4. Validation of instruments made under principal Ordinance 5. Omissions 2 TURKS AND CAICOS ISLANDS ELECTRICITY (VALIDATION) ORDINANCE 2018 (Ordinance 18 of 2018) Assent……………………………….……….……………..26th July 2018 Publication in Gazette……………...…………………3rd August 2018 Commencement………………………... in accordance with section 1 AN ORDINANCE TO VALIDATE THE COMMENCEMENT OF THE ELECTRICITY ORDINANCE FOR NORTH AND MIDDLE CAICOS AND OTHER PARTS OF THE TURKS AND CAICOS ISLANDS; AND FOR THE RATES AND CHARGES MADE THEREUNDER IN RESPECT OF THESE ISLANDS ENACTED by the Legislature of the Turks and Caicos Islands. Short title and commencement 1. This Ordinance may be cited as the Electricity (Validation) Ordinance 2018 and shall come into force on such day as the Governor may appoint by Notice published in the Gazette. Purpose 2. (1) The purpose of this Ordinance is to remedy the failure to bring into force the Electricity Ordinance to apply to North Caicos and Middle Caicos and the rest of the Turks and Caicos Islands. (2) The Electricity Ordinance was brought into force to apply to the islands of— (a) Grand Turk and Salt Cay on 1 April 1986; (b) South Caicos on 12 December 1986; and (c) Providenciales on 1 February 1987. 3 Validation commencement of principal Ordinance 3. (1) The principal Ordinance is deemed to have come into force for the islands of North Caicos and Middle Caicos and the rest of the Turks and Caicos Islands on 1 April 1986. (2) The principal Ordinance shall not be invalid in relation to North Caicos and Middle Caicos and the rest of the Turks and Caicos Islands by reason only of lack of an instrument made and published in the Gazette to bring into force the principal Ordinance in relation to those parts of the Islands. Validation of instruments made under principal Ordinance 4. (1) The Electricity Rates and Charges Regulations (Providenciales, North Caicos and Middle Caicos) are validated. (2) The rates and charges provided in the Electricity Rates and Charges Regulations (Providenciales, North Caicos and Middle Caicos) and any collections made thereunder or penalties imposed pursuant to those Regulations are validated and declared to have been lawfully made, collected or imposed, as the case may be, from 1 April 2012. Omissions 5. Any act or thing done or omitted to be done under the Electricity Ordinance in relation to North Caicos and Middle Caicos and the rest of the Turks and Caicos Islands, which would have been validly and properly done or omitted had the Ordinance been brought into force in respect of those parts of the Islands shall be deemed to be and have been validly and properly done thereunder.

Extraction Warnings

  • ⚠ The appointed commencement date under section 1 is not given in the supplied notice text; effective_date is therefore null.
  • ⚠ The notice text states an assent date and a Gazette publication date; notice_date is represented by the stated assent date.
Source: TCI Government Gazette Vol. 169, No. 33, published August 3, 2018. This is a research tool — verify information with authoritative sources before relying on it.